Projects › Lakeview Civic Campus (demo) › Dashboard

Lakeview Civic Campus (demo)

Construction · $46.5M

From the GMP to the anticipated final cost as of 31 October 2026

$46,500,000GMP+$420,000Approved ownerchanges+$600,000Ownercontingencydrawn+$73,200Open items,weighted+$62,000Allowanceoverruns-$30,000Projectedsavings$47,625,200Anticipatedfinal cost

The vertical scale starts below the GMP, not at zero, so the steps can be read. Every step comes from a register you can open above.

Contingency drawn over time as of 31 October 2026

$0$600,000$1,200,000Contractor fund $900,000Owner fund $1,200,000Contractor $450,000Owner $600,000Feb 26Mar 26Apr 26May 26Jun 26

One line per fund. The dashed thresholds are the two funds as set in the baseline. Lines differ in weight and dash as well as color, so the chart survives a grayscale print.

Change orders by cause, and who pays as of 31 October 2026

Design gap$186,000Contractor fund, 1 itemCoordination$0Contractor fund, 0 itemsOwner scope$420,000GMP, owner change, 1 itemUnforeseen$360,000Owner contingency, 1 itemUnclassified$244,000Undecided, 2 items

The payer follows the contract rule the change order register already applies. Unclassified has no payer yet, which is why it carries the flag color.

Flags 4 open, as of 31 October 2026

2 open items past the notice deadline with no notice on record.
A claim can be rejected on timing alone. This is a money event, not an administrative one.
2 items unclassified past 30 days, $244,000 total unclassified.
Money sitting between the two ledgers. It does not classify itself.
1 allowance past the decision deadline.
Every open day is a day the real number can move against the carried one.
5 contingency draws with no backup document.
Flagged, not blocked. The register shows which.